Free cookie consent management tool by TermsFeed Upgrading RWM [Robotic Workforce Manager v4.3]
Page not found in the selected version; redirected to the home page.
Upgrading RWM
The RWM application was deprecated with Appian 24.1. The application will no longer be updated or pre-installed for new Appian Cloud sites with Appian RPA enabled.

RWM will be removed in a future release and we encourage customers to use the Operations Console to manage robots instead.

Introduction

This guide will walk you through how to upgrade RWM 4.3.0 to 4.3.1.

Prerequisites

  • An installation of the Appian Platform
  • RWM 4.3.0 installed in a given environment, including database objects and plugins.

Downloading the RWM upgrade patch

  1. Click here to download the RWM 4.3.1 patch. This includes the following objects:
    • SQL Server - Patch - 4.3.1.sql: Microsoft SQL Server specific database updates. Ignore if not using SQL Server.
    • MySQL - Patch - 4.3.1.sql: SQL Server specific database updates. Ignore if not using MySQL.
    • Robotic WorkForce Manager - Patch - 4.3.1.zip: patch containing the updated Appian objects.
    • RWM v4.3.1.bprelease: package containing updated and new Blue Prism objects required for RWM 4.3.1.

Importing the SQL Database scripts

  1. In your business database, run either SQL Server - Patch - 4.3.1.sql or MySQL - Patch - 4.3.1.sql file, depending on your database vendor.

Importing the application package

  1. Navigate to Appian designer, and select the application Robotic Workforce Manager.
  2. Select Import Patch.
  3. Upload Robotic Workforce Manager - Patch - 4.3.1.zip.
  4. Click Import.

Importing the Blue Prism release package

  1. Before importing the release file, make sure that the schedules named RWM ETL Scheduler and RWM Schedules are retired.

  2. Choose File > Import > Choose Input File.

  3. Click Browse.
  4. Select the RWM v4.3.1.bprelease file.
  5. Click Next, and make sure the option Overwrite the existing process with the incoming process is selected for all objects.

  6. Click Next several times then click Finish.

Complete Blue Prism Post-setup steps

Complete the steps listed in section Post-setup steps in the Blue Prism set up instructions.

Additional Configuration

BPM processes and sessions are fetched through the process models RWM HB BPM Sessions and RWM HB Dump BPM Process Models. Set RWM_BPM_FLAG constant to true to turn on the data sync for Appian BPM processes.

Open in Github Built: Fri, May 10, 2024 (11:26:09 PM)